Notification Letter for General Order for Electricity Reliability Standards

File: OF-Fac-ElecGen-Rel-IPL 05
6 December 2012

To: Certain International Power Line (IPL) companies under the jurisdiction of the National Energy Board

Order for Electricity Reliability Standards

This letter is to notify you that the National Energy Board (NEB or Board) has issued an Order which imposes mandatory reliability standards on certain IPL companies under the Board’s jurisdiction. The Order comes into effect immediately and applies to NEB-regulated IPLs participating in the power system in North America, used for import and export of electricity operating at voltages of 100 kV and above, and some 69 kV power lines.

The IPL companies to whom the Order applies appear below; these are 32 certificate holders and five permit holders. General Order MO-036-2012 has been issued for the certificate holders, and Amending Orders have been issued to amend the applicable permits.  The provisions for the General Order and Amending Orders (the Order) are the same.

The Order addresses the regulatory gap for mandatory reliability standards that exists for IPLs between upstream provincial governance and the downstream United States jurisdiction. The provisions for the Order contain 12 reliability standards requirements, which correspond to the main categories of reliability standards developed by the North American Electric Reliability Corporation. The requirements are defined broadly so that they may include regional variations and can be harmonized with provincial regulatory frameworks as they relate to reliability standards.

On 23 February 2011, the NEB issued draft provisions for an order containing mandatory reliability standards for comment. The Board received submissions from the Canadian Electricity Association and seven IPL owners. Further comments were also received through follow-up meetings. The Board has considered all these comments and submissions. The Board has provided further remarks in respect of these comments and submissions. In addition, further information is provided in a set of Questions and Answers.

If you have any questions or require further information on this matter, please contact Tab Gangopadhyay at 403-299-3611 (tab.gangopadhyay@neb-one.gc.ca). You can also reach us by calling 1-800-899-1265.

Yours truly,

Sheri Young
Secretary of the Board

Attachments

Applicable Certificates and Permits

The General Order for mandatory electricity reliability standards applies to the following:

Applicable Certificates and Permits
Province Owner / Operator Certificate No. Line Designation Line Parameters (kV) No. of IPLs
British Columbia BC Hydro EC-III-12 5L51 500 1
  BC Hydro EC-III-04 5L52 500 1
  BC Hydro EC-III-10 2L112 230 1
  Teck Cominco Metals Ltd. EC-III-01 C51 230 1
Saskatchewan Saskatchewan Power Corporation EC-III-19 B10T 230 1
Manitoba Manitoba Hydro EC-III-16   500 1
  Manitoba Hydro EC-III-09 Y2OP 230 1
  Manitoba Hydro EC-III-14 R40M 230 1
Ontario Hydro One Networks Inc. EC-III-6 L4D 345 1
  Hydro One Networks Inc. EC-III-13 L51D 345 1
  Hydro One Networks Inc. EC-III-20 PA301, PA302 230 2
  Hydro One Networks Inc. EC-18 L33P 230 1
  Hydro One Networks Inc. EC-11 L34P 230 1
  Hydro One Networks Inc. EC-13 J5D 230 1
  Hydro One Networks Inc. EC-12 B3N 230 1
  Hydro One Networks Inc. EC-16 BP76, PA27 230 2
  Hydro One Networks Inc. EC-14 BSC105N 69 1
  Hydro One Networks Inc. EC-15 BSC105S 69 1
  Hydro One Networks Inc. EC-17 BL104 115 1
  Hydro One Networks Inc. EC-17 BSH-106 69 1
New Brunswick New Brunswick Power Transmission Corporation EC-III-08 301 345 1
  New Brunswick Power Transmission Corporation EC-III-25   345 1
  New Brunswick Power Transmission Corporation EC-III-18   138 1
  Algonquin Power EC-III-2 Tinker 6904 69 1
  Algonquin Power EC-III-3 Tinker 6901 69 1
Québec Hydro-Québec EC-III-15 7040 765 1
  Hydro-Québec EC-III-21 451 - 452 +/- 450 DC 1
  Hydro-Québec EC-III-17 1400 120 1
  Cedars Rapids Transmission Company Ltd. EC-III-24   120 1
  Hydro-Québec EC-III-22   120 1

Amending Orders for mandatory electricity reliability standards apply to the following:

Amending Orders for mandatory electricity reliability standards apply to the following
Province Owner / Operator Certificate No. Line Designation Line Parameters (kV) No. of IPLs
Alberta Montana-Alberta Tie Ltd. EP-301   243 1
Manitoba Manitoba Hydro EP-196 Glenboro 230 1
Ontario Hydro One Networks Inc. EPE-59 Fort Frances East 115 1
  Hydro One Networks Inc. EPE-113 Fort Frances West 115 1
  Canadian Niagara Power Inc. EP-137 Line 7 115 1

Note: separate Amending Orders have been issued for each of the five permit holders above.