ARCHIVED - NEB lifts pressure restriction on two sections of the TransMountain Pipeline - 24 March 2014

This page has been archived on the Web

Information identified as archived is provided for reference, research or recordkeeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

The Board has considered KMC’s requests dated 7 February 2014 and 20 February 2014 to lift the pressure restriction imposed under Condition 1 of the Safety Order on two segments of the TMPL, namely, Edmonton to Edson, Alberta, and Hinton, Alberta, to Hargreaves, British Columbia.

Based on the Board’s review of KMC’s submissions, including engineering assessments, the Board finds that KMC has complied with all the commitments outlined in its Integrity Assurance Plan, dated 9 July 2013, and Condition 5 of the Safety Order for the two TMPL segments aforementioned.