Filing Manual - Chapter 4 - Physical Projects
An applicant must:
- complete the common application requirements outlined in Chapter 3;
- confirm that the application is for a physical project;
- address section 4.1 - Project Description and section 4.2 - Economic
Feasibility, Alternatives and Justification; and
- identify which Guides within Chapter 4 are applicable (see Figure 2-1)
and provide the required information.
4.1 PROJECT DESCRIPTION
Goal
The application will include a clear description of the project, including:
- project components, activities and location;
- cost information;
- construction schedules; and
- related undertakings.
Filing Requirements
1. Identify and describe the project components, activities and related
undertakings (e.g., pipe, valves, compressors, pumps, access roads and construction camps).
2. Describe the project location and the criteria used to determine the proposed route or site.
3. Describe how and when the project will be carried out.
4. Provide a description of any facilities to be constructed by others
which are required to accommodate the proposed facilities.
5. Provide an estimate of the total capital costs and incremental
operating costs, if applicable, for the following categories:
- pipelines;
- compression or pumps;
- metering and regulating;
- tankage;
- other facilities;
- allowance for funds used during construction (AFUDC) including rates used; and
- capitalized overhead, showing a separate breakdown of the main
cost elements such as materials, installation, land and land rights.
6. Indicate the expected in-service date.
Guidance
Description of Project Components
The description of the project components should address the following:
- what the project is, including:
- a complete list and thorough description of the project components
and activities, including any components or activities required
for the project to proceed (e.g., construction camps, means of
access, electrical grid connections);
- the location and size of any temporary work space;
- a description of replacements or expansions of physical works
and activities that are anticipated over the life of the project; and
- preliminary drawings if available.
- where the project is located, including:
- a general description of the route or facility location, including
identification of:
- general land tenure;
- current land uses;
- nearest residences and communities;
- unique features;
- the positioning of project endpoints for linear developments;
- the location of any alternate routes or sites considered; and
- preliminary drawings, if available.
- how the project will be carried out, including:
- a thorough description of how project activities (e.g., clearing,
hydrostatic testing, watercourse crossings, inspection, monitoring
and surveillance programs) would be carried out during the construction
and operations phases;
- the anticipated workforce (i.e., person days and skills required
for construction and operations activities); and
- a list of other permits, licences, or authorizations that will
be required before part or all of the project can proceed.
- when the project would likely be carried out, including:
- a breakdown of all construction and operations activities by major activity;
- construction and operations schedules;
- a description of how any changes to schedules can affect the project; and
- a description of when proposed decommissioning and abandonment
of the project might take place.
4.2 ECONOMIC FEASIBILITY, ALTERNATIVES AND JUSTIFICATION
Goal
The application demonstrates the economic feasibility of the proposed project, any alternatives evaluated, and the justification for the proposed project.
4.2.1 Filing Requirement - Economic Feasibility
Describe the economic feasibility of the project.
Guidance - Economic Feasibility
The discussion of economic feasibility should integrate information provided elsewhere in the application with information provided under Guide A, Subsection A.3 - Economics, to show that the applied for project is economically feasible.
4.2.2 Filing Requirements - Alternatives and Justification
1. Describe the need for the project, other economically-feasible alternatives to the project examined, along with the rationale for selecting the applied for project over these other possible options.
2. Describe and justify the selection of the proposed route and site including a comparison of the options evaluated using appropriate selection criteria.
3. Describe the rationale for the chosen design and construction methods. Where appropriate, describe any alternative designs and methods evaluated and explain why these other options were eliminated.
4. For projects subject to a CEA Act environmental assessment and for which "alternatives to" the project or "alternative means" are relevant factors to be considered, describe these in the project Environmental and Socio-economic Assessment (ESA).
FYI - Additional information...
See Subsection A.2.3 - Scope of the Environmental and Socio-Economic Assessment for information about "alternatives to the project" and "alternatives means" under the CEA Act. |
Guidance - Alternatives
Alternatives Evaluated
In the context of economic feasibility, alternatives are other technically, economically and environmentally-feasible means of meeting the need for the project, such as a different:
- transportation mode;
- transmission system that could achieve the same purpose as the proposed facilities;
- route or site;
- facility design; or
- construction method, including different means of development, implementation and mitigation.
Selection Criteria
Different project, routing, design and construction alternatives must be summarized and compared using criteria that justify and demonstrate how the proposed option was selected and why it is the preferred option. The level of detail provided by the applicant may reflect the more conceptual nature of the options.
When comparing project routing, design or construction options, elaborate on the following criteria, as appropriate:
- engineering design;
- economic feasibility or costs;
- effect on reliability and security of the existing system;
- demonstrated public concern; and
- environmental and socio-economic constraints or potential effects.
4.2.3 Filing Requirement - Justification
Provide a justification for the proposed project.
Guidance - Justification
Describe the needs that would be satisfied by the project and demonstrate that, taking into consideration all viable alternatives available, the proposed project is the most appropriate option to meet the needs while serving the public interest.
Next Steps...
Determine which of the Guides included within this chapter are
applicable to the application being filed and complete the necessary
filing requirements. |