Stream 3 Actions Progress Report
Pipeline Abandonment - Financial Issues (Hearing RH-2-2008)
April 2010
Action 3.1 - RH-2-2008 Decision released |
||
| LMCI Actions | Tasks and Deliverables | Status |
|---|---|---|
3.1 RH-2-2008 Reasons for Decision Discussion of principles, high level Framework, Action Plan, Preliminary Base Case by NEB. |
Completed Tasks: Reasons for Decision RH-2-2008 [Filing A21835] |
|
Action 3.2 - Board Technical Conference on Preliminary Base Case |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.2 NEB Technical Conference Potential refinements to Preliminary Base Case. Participants to include: Group 1 and Group 2 companies that wish to attend, and any other interested person. |
Completed Tasks: NEB Technical Conference held on 17 November 2009 [Folder 566018] Conference Report sent to participants on 17 November 2009 for reply comments. |
|
Action 3.3 - Release of Refined Base Case |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.3 Release of Refined Base Case NEB to issue the Refined Base Case for Group 1 and Group 2 company use. As explained in the two releases, Board staff will consult with parties to develop a draft of unit cost values for discussion at a Fall 2010 meeting. To express interest in participating in the initial discussions, please contact Karine Simard (karine.Simard@neb-one.gc.ca). |
Completed Tasks: Released Refined Base Case [Filing A24600] Board 29 March 2010 letter [Filing A24839] |
|
Action 3.4 - Group 1 companies to file preliminary abandonment cost estimates using Base Case or pipeline-specific assumptions |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.4 Group 1: File Preliminary Estimates Option (a) - Group 1 companies each prepare and file an estimated of abandonment costs and the amount required to be set aside using the Base Case assumptions. or Option (b) - Group 1 companies each prepare and file, for approval, an estimate of abandonment costs and the amount required to be set aside using pipeline-specific assumptions or a combination of pipeline-specific and Base Case assumptions. |
Upcoming Tasks: To be determined |
|
Action 3.5 - NEB decisions on Group 1 companies' preliminary estimates |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.5 Group 1: NEB Decisions on Estimates NEB consideration of Group 1 companies' preliminary estimates that use pipeline-specific assumptions or a combination of pipeline-specific and Base Case assumptions. |
Upcoming Tasks: To be determined |
|
Action 3.6 - Group 1 companies to file proposed collection mechanisms and proposed set aside mechanisms |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.6 Group 1: File Proposed Mechanisms Group 1 companies each develop and file, for approval, a proposal for collection of funds and a proposed process and mechanism to set aside the funds [can be combined with Action 3.4 and filed by 31 May 2011]. |
Upcoming Tasks: To be determined |
|
Action 3.7 - Group 2 companies to file preliminary estimates using Base Case or pipeline-specific assumptions |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.7 Group 2: File Preliminary Estimates Group 2 companies each prepare and file an estimate of abandonment costs and the amount required to be set aside using either the Base Case or pipeline-specific assumptions. |
Upcoming Tasks: To be determined |
|
Action 3.8 - Group 2 companies to file proposed collection mechanisms |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.8 Group 2: File Collection Mechanisms Group 2 companies that charge tolls each develop and file a proposal for collection of funds [can be combined with Action 3.7 and filed by 30 November 2011]. |
Upcoming Tasks: To be determined |
|
Action 3.9 - Group 2 companies to file proposed set aside mechanisms |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.9 Group 2: File Set Aside Mechanisms Group 2 companies each file with the Board a proposed process and mechanism to set aside funds [can be combined with Action 3.7 or 3.8, and filed at the earliest applicable date]. |
Upcoming Tasks: To be determined |
|
Action 3.10 - NEB decisions on Group 1 companies' mechanisms for collection and set aside of funds |
||
| LMCI Actions | Tasks and Deliverables | Status |
3.10 Group 1: Decisions on Mechanisms NEB consideration of Group 1 companies proposals for collection and set aside mechanisms. |
Upcoming Tasks: To be determined |
|
Legend:
Completed
In Progress
Timing TBD
Due Date