NOVA Gas Transmission Ltd. – 2021 NGTL System Expansion Project

What’s New

  • September 20, 2018: NEB releases opportunity for Participants to provide comment by October 18 [Filing A94100]
  • September 20, 2018: NEB issues Ruling No. 1 – Participation in the Hearing [Filing A94099]
  • August 17, 2018: Apply to participate has closed

Project Information

NOVA Gas Transmission Limited (NGTL), a wholly owned subsidiary of Trans Canada, has filed an application for the 2021 NGTL System Expansion Project. A project description is not an application; it provides preliminary information about an application the company expects to file at a later date. NGTL proposes to build and operate approximately 350 km of 1,219 mm (NPS 48) outside diameter natural gas pipeline and associated facilities in northwestern Alberta. If approved, the project would “loop” or add new pipeline parallel or adjacent to, the existing NGTL System.

The Project includes three main areas:

Grande Prairie West Area:

  • Grande Prairie Mainline Loop No. 4 (Valhalla Section), approximately 38 km; and,
  • Grande Prairie Mainline Loop No. 3 (Elmworth Section), approximately 47 km.

Grande Prairie South Area:

  • Grande Prairie Mainline Loop No. 2 (Karr Section), approximately 57 km;
  • Grande Prairie Mainline Loop No. 2 (Deep Valley Section), approximately 68 km; and,
  • Grande Prairie Mainline Loop No. 2 (McLeod River Connection Section), approximately 15 km.

Edson South Area:

  • Edson Mainline Loop No. 4 (Rob Section), approximately 42 km;
  • Edson Mainline Loop No. 4 (Dismal Creek Section), approximate4ly 33 km;
  • Edson Mainline Loop 4 (Brewer Section), approximately 50 km;
  • Three compressor station unit additions at Nordegg, AB, Didsbury, AB and Beiseker, AB; and,
  • January Creek Control Valve and associated pipeline tie-ins.

In its application, NGTL said the project was needed to transport natural gas from areas of increasing production in northwestern Alberta and northeastern BC to intra-Alberta and export markets. If approved, NGTL plans to begin operating the project by April 2021.

Project Map

This map provides an overview of the project.

NOVA Gas Transmission Ltd. – 2021 System Expansion Project Map

View larger PDF version [PDF 402 KB]

Key Milestones

  • July 16 – August 17, 2018: Apply to Participate

  • June 21, 2018: NGTL filed their project application [Filing A92619]
  • February 27, 2018: NGTL submits its project description [Filing A90239]

Preliminary List of Issues

The Board has identified the following issues for consideration in the hearing with respect to the construction and operation of the proposed 2021 System Expansion Project:

  1. The need for the Project.
  2. The economic feasibility of the Project.
  3. The potential commercial impacts of the Project.
  4. The appropriateness of the toll and tariff methodology of the Project.
  5. The potential environmental and socio-economic effects of the Project, including any cumulative environmental effects that are likely to result from the Project as set out in the NEB’s Filing Manual, as well as those to be considered under the Canadian Environmental Assessment Act, 2012 (see Appendix D).
  6. The appropriateness of the general route and land requirements for the Project.
  7. Potential impacts of the Project on IndigenousFootnote 1 interests.
  8. Potential impacts of the Project on owners and users of lands
  9. The suitability of the design of the Project.
  10. Contingency planning for leaks, accidents or malfunctions, during construction and operation of the Project.
  11. Safety and security during construction and operation of the Project, including emergency response planning and third-party damage prevention.
  12. The terms and conditions to be included in any recommendation or approval the Board may issue for the Project.

Resources

If you would like to learn more about the NEB’s hearing process, please visit the following links:

Apply to Participate

Attention

Email is not a valid method of filing regulatory documents with the NEB. Comments received by email will not be considered. You must apply to participate.

To be a participant in a NEB hearing process, you must be directly affected or have relevant information or expertise. You can apply to participate as an intervenor or by letter of comment.

The application to participate process was held from July 16 – August 17, 2018.

The process is now closed. If a late submission is required, please contact the process advisor to discuss requirements. The NEB will decide if late applications will be accepted.

You can contact a process advisor by calling 1-800-899-1265 (toll free) or emailing NGTLExpansion@neb-one.gc.ca.

Participant Funding

Participant funding is available to facilitate the participation in this public hearing. Refer to the Participant Funding Program page for information on deadlines, eligibility, how to apply for funding, and how to submit claims.

Process Advisor – Support to Hearing Participants

For assistance, participants may contact the Board’s Process Advisory Team for this Project at NGTLExpansion@neb-one.gc.ca or by telephone toll-free at 1-800-899-1265.

Contacts

NEB Contacts

For process-related inquiries, please contact:

Process Advisor Team
National Energy Board
Email: ngtlexpansion@neb-one.gc.ca
Telephone (toll free): 1-800-899-1265
Facsimile: 403-292-5503
Facsimile (toll free): 1-877-288-8803
TTY (Teletype): 1-800-632-1663

For media inquiries, please contact:

Media Relations team
National Energy Board
media@neb-one.gc.ca

Date modified: